MEETING OF CLONDALKIN AREA COMMITTEE
Wednesday, June 22, 2016
MOTION NO. 15
MOTION: Councillor F. Timmons
Cathaoirleach’s Business
“That a report be issued into Roadstone quarry and reports of worrying movement and tremors in the Hazelwood area at Green Isle are commented on.”
REPORT:
Following the review and determination of all quarries in the county in 2012 an application for Substitute Consent was made by Roadstone to regularise development at the Belgard Quarry. This application remains to be determined by An Bord Pleanála.
An application for further development, continued use and extension by deepening of an area (18.2 hectares) of overall site of the quarry to 5m OD has also been submitted to An Bord Pleanála. This application also remains to be determined. South Dublin County Council has made observations on both applications to An Bord Pleanála.
The quarry operator has been submitting regular monitor results from the quarry operations in respect of dust, water quality and vibration. The results are generally within established limits.
The Planning Authority has no record of any complaints of movement and tremors in the Hazelwood area at Green Isle.
300-101 400-101 300-320 300-070 300-206 200-310 300-135 300-208 810-403 400-050 640-916 642-997 300-209 400-201 200-355 352-001 642-999 350-080 MB2-712 400-051 C2150-606 1Z0-434 1Z0-146 C2090-919 C9560-655 642-64 100-101 CQE CSSLP 200-125 210-060 210-065 210-260 220-801 220-802 220-901 220-902 2V0-620 2V0-621 2V0-621D 300-075 300-115 AWS-SYSOPS 640-692 640-911 1Z0-144 1z0-434 1Z0-803 1Z0-804 000-089 000-105 70-246 70-270 70-346 70-347 70-410