MEETING OF CLONDALKIN AREA COMMITTEE
Wednesday, April 20, 2016
QUESTION NO. 8
QUESTION: Councillor F. Timmons
“To ask the Chief Exectutive for an update report on work on the Tower Heritage centre?”
REPLY:
Tenders have been received and evaluated for the construction of the Visitor Centre. A contract will be signed in the coming fortnight and construction on-site will begin in the week commencing 9th May. Works will be completed within twelve months. Archaeological excavations on-site are now completed and a report will be prepared for the National Museum on all the findings.
The second stage of the tender for Café / Retail franchise has issued. A tender for the exhibition-content and design will issue in the next fortnight.